Sr. No. Project Name Cost of Work
(INR in Crores)
Work Status
1 External Electrification Work of HT LT Line and Transformer, Line Shifting at Various Places in ABD area and Pan City Area under Indore Smart City Project. Phase 3 1.44 Work in progress
2 ReDevelopment of Nehru Park , Indore  7.96 Work in progress
3 Construction of Amphitheater in Gopal Mandir Campus including Civil, structural, acoustic, electrical, audio video system and air-conditioning 11.28 Work in progress
4 Design,Construcation of Elevation works for transit management centre building,AICTSL Campus,Indore 0.66 Work in progress
5 Selection of Consultant for developing designing an integrated surveillance plan for Indore city 2.12 Work in progress
6 Redevelopment of MOG Lines area – MOG Barracks Land Parcel under PPP model 19.60 Work in progress
7 Redevelopment of MOG Lines area – Kukkut Palan Kendra Land Parcel under PPP model 0.13 Work in progress
8 Infrastructure development for the campus of mixed use real estate redevelopment projects at MOG Line- old Govt quarters. 9.06 Work in progress
9 Selection of Agency for Parking at Khajuri Bazar  6.75 Work in progress
10 Selection of Agency for Parking at Veer Savarkar Market  17.54 Work in progress
11 Riverfront Development – Jawahar Bridge to Chandrabhaga Bridge 2.18 Work in progress
12 Riverfront Development – Harsiddhi Bridge to Gangour Bridge  8.80 Work in progress
13 Riverfront Development – Jairam Bridge to Lal Bagh Bridge 10.92 Work in progress
14 Design and Construcation of Bridge for Pedestrians Movement and Stop Dam on River Saraswati at Harsiddhi Park 4.93 Work in progress
15 Develp. of Integrated Smart Road Network i c Jawahar Marg Bridge in ABD Area Indore under SCM 0.93 Work in progress
16 Development of integrated smart road network in ABD area under smart city mission-Package 1 43.42 Work in progress
17 Development of integrated smart road network in ABD area under smart city mission-package -5 15.99 Work in progress
18 Underground Cabling Works with Compact Type Sub-Stations for various roads in ABD area using existing equipment From Gangwal Bus Stand to Silawatpura Dargaha under Indore Smart City Project Second call 2.75 Work in progress
19 Development of Smart Road from Badaganpati Square to Krishnpura Bridge MG Road Including Underground Electric cabling 37.41 Work in progress
20 Underground cabling work with compact type substation of various road in ABD area Pan City Area using existing and new equipment’s under Indore Smart City Project. Package E7 7.93 Work in progress
21 Constucation of police thanan at old M.G Road,Indore 1.04 Work in progress
22 Construction of Pedestrian Bridge – near Harsiddhi Park  4.68 Work in progress
23 Construction of Multipurpose building, phase 1 in place of old Marathi school under smart city mission at MG Road indore 26.44 Work in progress
24 Solar Power Plant _ Jalud Consultancy  6.00 Work in progress
25 Selection of Master System Integrator MSI for Implementation of Intelligent Integrated Traffic Management System ITMS for ISCDL 34.25 Work in progress
26 Providing ,Supplying,Laying of sewer collection system & connecting existing or new house service connection to the proposed or existing system in CP Sekher Nagar Sewer Zone (Pak.2) 20.02 Work in progress
27 Providing ,Supplying,Laying of sewer collection system & connecting existing or new house service connection to the proposed or existing system in Chhatri Bhag Area (Pak.3) 10.81 Work in progress
28 Providing ,Supplying,Laying of sewer collection system & connecting existing or new house service connection to the proposed or existing system in Shubhash Chowk Sewer Zone (Pck.1) 27.42 Work in progress
29 Providing ,Supplying,Laying of sewer collection system & connecting existing or new house service connection to the proposed or existing system in Jinsi (Pck.4) 6.05 Work in progress
30 SELECTION OF AGENCY FOR OPERATION AND MAINTENANCE OF 10 MLD SBR BASED STP (MPS, PUMPING MAIN ETC.) AND 33/0.415 KV SUBSTATION, COMPRISING OF ALL CIVIL, ELECTRICAL, MECHANICAL AND OTHER ALLIED WORKS AND UTILITIES INCLUDING DEPLOYMENT OF SPECIFIED STAFF AND INSTALLATION OF DG SET, ONLINE CONTINUOUS EMISSION MONITORING SYSTEM AND RECTIFICATION OF OTHER NECESSARY EQUIPMENT AT HARSIDDHI INDORE. 8.05 Work in progress
31 Selection of EPC Contractors for Remaining Work of Providing, Supplying, Laying, Testing of Water Supply System & Connecting Existing / New House Service Connection (HSC) To The Proposed/ Existing System in ABD Area 31.46 Work in progress
32 PACKAGE -1: CHHATRIBAGH  OHT AND C.P SHEKHAR NAGAR OHT 29.02 Work in progress
33 Selection of EPC Contractors for Remaining Work of Providing, Supplying, Laying, Testing of Water Supply System & Connecting Existing / New House Service Connection (HSC) To The Proposed/ Existing System in ABD Area 8.63 Work in progress
34 Survey,Investigation,Engineering,Procurement,Design,Constructing and Completing the facilities to reach the treated effluent up to end user from outlet of 245MLD STP and sale treated effluent for irrigation,industries and other non-domestic purpose etc with 15 years operation & maintenance etc complete on deferred payment basis 25.89 Work in progress
35 Construction of Shopping Complex in Bakshi Gali near Veer Savarkar Market, Indore 1.52 Work in progress
36 Construction of Shopping Complex infront of Veer Savarkar Market, Indore 1.59 Work in progress
37 Design and Construcation of Roofing Shed for Solar Panels and Lift Structure works on ICCC Building,AICTSL Campus,Indore 0.26 Work in progress
38 Selection of EPC contractor for Design, Supply,Installation,Testing and Commissioning of the electrical lighting network including lighting fixture with 3 years operation and maintenance at Nehru Park 1.49 Work in progress